Demolition





December 2022 : Old building Demolition finish
Foundation Ready



Feb 2023 : Smithfield Industrial Park: A well-designed and properly constructed foundation. It is the excellent work of our professional team, who consistently deliver high-quality results and exceed expectations.
Tilt Up Concrete Panel



April 2023: Smithfield Industrial Park is benefit of tilt-up wall panels is that they are load-bearing. This means they do not need perimeter columns or roof beams, typically needed with precast concrete projects. This allows for greater flexibility for exterior openings and design changes, such as cutting windows to improve lighting or wall sawing a doorway for an industrial roller door. Speed and Good quality also Reduce energy operating costs : superior thermal performance that conserves energy
Concrete wall instalation




May 2023:Type A warehouse finish top up, Type B and Type D warehouse are coming.
Keep doing good job!





25 July 2023 The progress is lightning-fast.
Tilt-up keep going !




13 September 2023 All ware house concrete wall have been tilted up!
Last block nearly finish





20 October last block tile up and installing the roof.
hardworking before christmas





December 2023 hardworking before christmas, Hey guys, good on you, amazing speed and quality.
Final stage!




Final stage!
Occupancy Certificate is ready!




Congratulations to the owner of Smithfield Industrial Park the OC is ready!